Remove Current Earned Values
Use this option to clear the current reporting period earned values. This may be necessary to correct errors in the data for the current reporting period.
- Select in the Navigation Menu. The main EVMax window displays.
- Select your project from the dropdown in the Ribbon Menu.
- Select the Admin tab.
- Click the dropdown in the Ribbon Menu and then click . A Remove Earned dialog box displays.
- Accept the default setting in the dropdown. The default is the current reporting period end date.
- Click . The current reporting period earned values are deleted.
What to Do Next
- Manually enter the current status again (Work Package tab, Status EVT tab) to recalculate the earned value data you just deleted. See Status Work Packages or Status Material Work Packages. Also see Generate Earned if you have any work packages assigned the earned value technique Earned as Spent.
- If you have integrated your schedule and cost data, Import Schedule Status again to recalculate the earned value data.